Narembeen Mains Replacement
Katanning, Western Australia
Jun 2020 - Jul 2020 (4 Weeks)
Replacement of existing MS20C Main due to the condition of the main.
Replacement of approx. 60m of Main with new DN150 MSCL Pipe. Working within community boundaries the works were completed on time and under budget achieving 20% Aboriginal business Spend and over 50% Aboriginal Employment at all times on site.
Peak Personnel: 6
ATSI participation: 50%
No Lost Time Injuries
No Environmental Incidents