Kalgoorlie Potable Water Dam Civil Works

Kalgoorlie, Western Australia
Jul 2022 – Jan 2023

Scope

The Works Under Contract (WUC) primarily involve:

  • Reducing the reservoir overflow level by cutting and removal of a section of the overflow structure.
  • Supply and installation of exclusion barrier at the reservoir over structure.
  • Placement of fiber reinforced shotcrete to increase the life of the spillway chute.
Peak Personnel: 10
ATSI participation: 20%
No Lost Time Injuries
No Environmental Incidents
Back to Projects