Herdsman Lake Civil & Drainage
Herdsman Lake, Western Australia
Jan 2021 – Dec 2021
The Works under the Contract consisted of supply and construction of drainage infrastructure and assets.
The works have been divided into 3 packages (sites), the scopes for each package are detailed in the points below:
- Installation of Principal Supplied Litter Boom (3 on 3 different locations)
- Construction of 12 pile anchors (3m deep at average under water table)
- Construction of limestone hardstand area (500m2)
- Construction of access platforms
- Supply and construction of an extension of fences near headwalls (3 on 3 different locations)
- Supply and installation of bollards both permanent and removable along northern bank
- Supply and install rock protection on drain as detailed on the drawings (3 on 3 different locations).
- Restoration and reinstatement of disturbed areas
Peak Personnel: 10
ATSI participation: 10%
No Lost Time Injuries
No Environmental Incidents