Herdsman Lake Civil & Drainage

Herdsman Lake, Western Australia
Jan 2021 – Dec 2021

Scope

The Works under the Contract consisted of supply and construction of drainage infrastructure and assets.

The works have been divided into 3 packages (sites), the scopes for each package are detailed in the points below:

  • Installation of Principal Supplied Litter Boom (3 on 3 different locations)
  • Construction of 12 pile anchors (3m deep at average under water table)
  • Construction of limestone hardstand area (500m2)
  • Construction of access platforms
  • Supply and construction of an extension of fences near headwalls (3 on 3 different locations)
  • Supply and installation of bollards both permanent and removable along northern bank
  • Supply and install rock protection on drain as detailed on the drawings (3 on 3 different locations).
  • Restoration and reinstatement of disturbed areas
Peak Personnel: 10
ATSI participation: 10%
No Lost Time Injuries
No Environmental Incidents